Bang Concrete began forming the retaining walls on March 10, 2010, had the concrete poured and the next day March 11, they pulled the forms and here we have walls.....yay!
The next step while the retaining walls cured long enough to be backfilled against was the layout of the house and plumbing placed in the ground, that would happen on March 30, 2010.....
On April 2, 2010, the foundation floor to the house was poured. It is one BIG piece of concrete...
Just four days later on April 6, 2010 they delivered the forms to start forming the walls for the garage, three days later on April 9th we had garage walls standing....