The painters came in on Wednesday June 23 and finished the touch-ups and accent color wall on Saturday June 26....and here is the green color wall that is in the family room and the living room, and a room in the master bedroom....I LOVE IT!
And the stone work on the arches on the front of the house and the pillars out front of the bridge were finished on Saturday June 26.
And the kitchen cabinet doors were installed on Monday June 21.
The Electricians put all the ceiling fans and light fixtures up, July 1, 2010....
The Fireplace was finally finished, just a few more pieces to add, but the most of got done on July 1, 2010...beautiful!
The stair posts finally got installed on July 1, 2010 also....the wood still needs to be painted black, and then the wrought iron parts can be added....just one more step closer.
The granite kitchen counter tops were installed on June 30th...
Natural Beauty
Sunday, June 27, 2010
Saturday, June 19, 2010
The Fireplace
The drywall got done on the fireplace area....then we waited, and waited, and waited, and then.........on June 16, 2010 the built-in bookshelves were installed...totally awesome!
The Mantle was installed on Wednesday June 23rd.
July 1, 2010, the fireplace was nearly complete with the front panels being installed...just a few more trim pieces and it will be done.
The Mantle was installed on Wednesday June 23rd.
July 1, 2010, the fireplace was nearly complete with the front panels being installed...just a few more trim pieces and it will be done.
Saturday, June 12, 2010
Bathrooms
The Marble behind the tubs were installed and also the master suite marble shower was installed on Friday June 11, 2010.
Thursday, June 10, 2010
The Cabinets
The cabinets were all delivered on Wednesday June 9th......they just kept coming...The cabinets were made by Jess and his crew at Ideal Cabinets....they did a great job!
The cabinets were installed, minus the doors so far on June 11, 2010.
The cabinets were installed, minus the doors so far on June 11, 2010.
Sunday, June 6, 2010
UPDATES
Not really much to take photos of right now. The texture crew finished up on Thursday night ( June 3), and so on Friday the 4th the paint crew got in there and started and were finished painting on Saturday afternoon. Next comes wood flooring, and carpet. The cabinets should go in sometime around June 11th. So Exciting!