JW Horsley started framing the lower level on April 12, 2010, these guys were amazingly fast and did quality work, on April 13th they layed the floor truss for the top level and began to sheet the floor, on April 15th the steel beams for the garage floor were delivered and placed, and on April 19th JW and his crew (in one day) framed the whole main level of the house...WOW! all the neighbors were amazed...so at 6:30 pm on the 19th of April, the roof trusses were delivered.....
A few days later all the trusses were in place, and the roof was sheeted...wala..we have a house......
now just a few ictures from inside the framed house....