Doors/Windows/Roofing/Stucco (Page 6)

 On May 11, 2010 the first (11) doors all exterior were delivered...
On may 13th all the windows were delivered and then installed on May 14th...Yay!




On May 12, 2010,  the tile for the roof was delivered.....they had the tile layed on the roof the next day, the roofers were fast!

The stucco company was in there and out of there in two days, finishing up the lathe on the house......next comes first gray coat...
The gray coat was put on in one day....12 crew members and about six hours later, after they sprayed the coat on and smoothed it out! 

74 buckets of stucco color was delivered on Friday June 11, 2010. 
 